Creating a network diagram involves several steps:
1. List All Activities: Write down all the tasks required to complete the project. 2. Determine Dependencies: Identify which tasks depend on the completion of others. 3. Draw Nodes: For AON, draw a node for each task. 4. Connect Nodes: Use arrows to connect the nodes and show dependencies. 5. Estimate Durations: Assign time estimates to each task. 6. Identify the Critical Path: Calculate the longest path through the network, which represents the minimum project duration.